Navigation

Spring 2016 Lab Imaging & Update Schedule

September 7, 2015 -- The Spring 2016 Lab Imaging & Update Schedule is listed below.

Oct 07, 2015

  • October 19 - 30:
    • Review of computer classroom/lab schedules for Spring Term
    • Need documentation of academic software changes & updates for all computer classrooms/labs (Updated image management test plans due by October 30 COB)
    • Build/deploy Spring 2016 “test image” signs up on test systems in computer labs/classrooms
  • November 2 - 13:
    • Preparation of Spring 2016 test image is complete -- “Ready for testing” signs placed on select test systems in computer labs/classrooms
    • Test machine to be complete by ITS November 13
  • November 16 - 25:
    • Academic Chair, faculty and lab supervisors/staff begin review of Spring 2016 test image on selected test systems and  go through IMTPs to ensure all software is in place and functional.
    • Feedback corrections to ITS for Spring 2016 test images due November 25
  • November 30 – December 4:
    • Academic Chair, faculty and lab supervisors/staff conclude review of test image and instructional software
    • Corrections made to test image – retest instructional software as necessary. Completed by December 4.
  • December 7:
    • System images for Spring 2016 are “frozen” - Post signs: “Official Spring 2016 image for Room: __________”
  • December 7 – January 15:
    • ITS begins final deployment of system images in ALL computer labs/classrooms – image deployments to continue through January 15
  • January 15:
    • Deployment of final images complete